[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910501":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910501,587,2,"多选题","建设项目静态投资包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","基本预备费",true,{"key":16,"text":17,"correct":14},"B","设备和工器具购置费",{"key":19,"text":20,"correct":21},"C","涨价预备费",false,{"key":23,"text":24,"correct":21},"D","建设期贷款利息",{"key":26,"text":27,"correct":21},"E","投资方向调节税","AB","2020版教材P3 静态投资是指不考虑物价上涨、建设期贷款利息等影响因素的建设投资。静态投资包括：建筑安装工程费、设备和工器具购置费、工程建设其他费、基本预备费，以及因工程量误差而引起的工程造价增减值等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]