[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910479":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910479,587,2,"多选题","建设工程全要素造价管理是指除控制建设工程本身的建造成本外，还应同时考虑对建设工程（ ）的控制。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工期成本",true,{"key":16,"text":17,"correct":14},"B","质量成本",{"key":19,"text":20,"correct":21},"C","运营成本",false,{"key":23,"text":24,"correct":14},"D","安全成本",{"key":26,"text":27,"correct":14},"E","环境成本","ABDE","2020版教材P4 建设工程造价管理不能单就工程造价本身谈造价管理，因为除工程本身造价之外，工期、质量、安全及环境等因素均会对工程造价产生影响。为此，控制建设工程造价不仅仅是控制建设工程本身的成本，还应同时考虑工期成本、质量成本、安全与环境成本的控制，从而实现工程造价、工期、质量、安全、环境的集成管理。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]