[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910474":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910474,587,2,"多选题","施工合同签订后，工程项目施工成本计划的常用编制方法有（ ）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","专家意见法",false,{"key":16,"text":17,"correct":14},"B","功能指数法",{"key":19,"text":20,"correct":21},"C","目标利润法",true,{"key":23,"text":24,"correct":21},"D","技术进步法",{"key":26,"text":27,"correct":21},"E","定律估算法","CDE","2020版教材页码：P343。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]