[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910465":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910465,587,2,"多选题","在下列建设工程项目目标控制方法中，可用来综合控制工程进度和工程造价的方法有（ ）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","树枝图法",false,{"key":16,"text":17,"correct":14},"B","网络计划法",{"key":19,"text":20,"correct":21},"C","S 曲线法",true,{"key":23,"text":24,"correct":14},"D","决策树法",{"key":26,"text":27,"correct":21},"E","香蕉曲线法","CE","2020版教材页码：P102。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]