[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910464":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910464,587,2,"多选题","施工图预算审查的方法有（ ）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","全面审查法",true,{"key":16,"text":17,"correct":14},"B","重点抽查法",{"key":19,"text":20,"correct":14},"C","对比审查法",{"key":22,"text":23,"correct":24},"D","系数估算审查法",false,{"key":26,"text":27,"correct":24},"E","联合会审法","ABC","2020版教材页码：P312",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]