[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910452":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910452,587,2,"多选题","关于施工图预算的审查方法，下列说法正确的是（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","标准预算审查法适用于通用图纸施工且上部结构和做法相同的工程",true,{"key":16,"text":17,"correct":18},"B","筛选审查法不适用住宅工程",false,{"key":20,"text":21,"correct":14},"C","分组计算审查法能够加快审查工程量的速度",{"key":23,"text":24,"correct":14},"D","逐项审查法适用于工艺较简单的工程",{"key":26,"text":27,"correct":18},"E","利用手册审查法不能简化预结算的编审工作","ACD","2020版教材页码：P312",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]