[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910446":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910446,587,2,"多选题","某工程施工至某月底，经偏差分析得到费用偏差（CV）＞0，进度偏差（SV）＞0，则表明（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","已完工程实际费用节约",true,{"key":16,"text":17,"correct":18},"B","已完工程实际费用＞已完工程计划费用",false,{"key":20,"text":21,"correct":18},"C","拟完工程计划费用＞已完工程实际费用",{"key":23,"text":24,"correct":14},"D","已完工程实际进度超前",{"key":26,"text":27,"correct":18},"E","拟完工程计划费用＞已完工程计划费用","AD","本题考查的是工程费用的动态监控。CV=已完工程计划费用－已完工程实际费用，若 CV 大于零，证明工程费用节约，已完工程实际费用＜已完工程计划费用；SV=已完工程计划费用－拟完工程计划费用，SV 大于零，说明工程进度超前，拟完工程计划费用＜已完工程计划费用。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]