[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910442":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910442,587,2,"多选题","根据《标准施工招标文件》中的合同条款，需要由承包人承担的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","承包人协助监理人使用施工控制网所发生的费用",true,{"key":16,"text":17,"correct":14},"B","承包人车辆外出行驶所发生的场外公共道路通行费用",{"key":19,"text":20,"correct":21},"C","发包人提供的测量基准点有误导致承包人测量放线返工所发生的费用",false,{"key":23,"text":24,"correct":21},"D","监理人剥离检查已覆盖合格隐蔽工程所发生的费用",{"key":26,"text":27,"correct":21},"E","承包人修建临时设施需要临时占地所发生的费用","AB","本题考查的是《标准施工招标文件》中的合同条款。选项 CDE 属于发包人应承担的费用。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]