[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910418":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910418,587,2,"多选题","某工作双代号网络计划如下图所示，存在的绘图错误有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","多个起点节点",true,{"key":16,"text":17,"correct":18},"B","多个终点节点",false,{"key":20,"text":21,"correct":18},"C","存在循环回路",{"key":23,"text":24,"correct":14},"D","节点编号有误",{"key":26,"text":27,"correct":14},"E","有多余虚工作","ADE","在此图中会发现①、②均为起点节点，A 对；终点节点只有⑧，B 错；没有循环回路，C 错；箭头节点编号必须小于箭尾节点编号，故②? ③、⑦? ⑥是错误的，故 D 对；对于③? ⑤这个虚工作是多余的，可由③ 节点直接指向⑥节点，形成③? ⑥工作，故 E 正确。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]