[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910417":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910417,587,2,"多选题","在组织建设工程流水施工时，等步距异节奏流水施工的特点包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","同一施工过程中各施工段的流水节拍不尽相等",false,{"key":16,"text":17,"correct":18},"B","相邻专业工作队之间的流水步距全部相等",true,{"key":20,"text":21,"correct":14},"C","所有施工过程所有施工段的流水节拍全部相等",{"key":23,"text":24,"correct":18},"D","专业工作队数大于施工过程数，从而使流水施工工期缩短",{"key":26,"text":27,"correct":18},"E","各专业工作队在施工段上能够连续作业","BDE","本题考查的是异节奏流水施工。流水节拍同一施工过程相等，不同施工过程不尽相等，但存倍数关系。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]