[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910398":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910398,587,2,"多选题","为了有效地控制建设工程造价，造价工程师可采取的技术措施包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","重视工程设计多方案的选择",true,{"key":16,"text":17,"correct":18},"B","明确工程造价管理职能分工",false,{"key":20,"text":21,"correct":14},"C","严格审查施工组织设计",{"key":23,"text":24,"correct":18},"D","严格审查各项费用支出",{"key":26,"text":27,"correct":14},"E","严格审查施工图设计","ACE","本题考查的是工程造价管理的基本原则。从技术上采取措施，包括重视设计多方案选择，严格审查监督初步设计、技术设计、施工图设、施工组织设计，深入技术领域研究节约投资的可能性。选项 B 属于组织措施，选项 D 属于经济措施。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]