[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910387":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910387,587,2,"多选题","（2019年）某工程开工至第三个月末累计已完工程计划费用1200万元，已完工程实际费用1500万元，拟完工程计划费用1300万元，此时进行偏差分析可得到的正确结论有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","进度提前300万元",false,{"key":16,"text":17,"correct":18},"B","进度拖后100万元",true,{"key":20,"text":21,"correct":14},"C","费用节约100万",{"key":23,"text":24,"correct":14},"D","工程节约300万元",{"key":26,"text":27,"correct":18},"E","费用超过300万元","BE","费用偏差=已完工程计划费用-已完工程实际费用 进度偏差=已完工程计划费用-拟完工程计划费用 此题中：费用偏差=1200万元-1500万元=-300万元，表示费用超支300万元。 进度偏差=1200万元-1300万元=-100万元，表示进度滞后100万元。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]