[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910384":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910384,587,2,"多选题","(2015年)按工程项目组成编制施工阶段资金使用计划时，不能分解到各个工程分项的费用有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","人工费",false,{"key":16,"text":17,"correct":18},"B","保险费",true,{"key":20,"text":21,"correct":14},"C","二次搬运费",{"key":23,"text":24,"correct":18},"D","临时设施费",{"key":26,"text":27,"correct":14},"E","施工机具使用费","BD","本题考查的是资金使用计划的编制。建筑安装工程费用中的人工费、材料费、施工机具使用费等直接费，可直接分解到各工程分项。而企业管理费、利润、规费、税金则不宜直接进行分解。措施项目费应分析具体情况，将其中与各工程分项有关的费用（如二次搬运费、检验试验费等）分离出来，按一定比例分解到相应的工程分项；其他与单位工程、分部工程有关的费用（如临时设施费、保险费等），则不能分解到各工程分项。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]