[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910382":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910382,587,2,"多选题","(2013年)某工程施工至某月底，经偏差分析得到费用偏差(CV)＜0，进度偏差(SV)＜0，则表明()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","已完工程实际费用节约",false,{"key":16,"text":17,"correct":18},"B","已完工程实际费用＞已完工程计划费用",true,{"key":20,"text":21,"correct":14},"C","拟完工程计划费用＞已完工程实际费用",{"key":23,"text":24,"correct":14},"D","已完工程实际进度超前",{"key":26,"text":27,"correct":18},"E","拟完工程计划费用＞已完工程计划费用","BE","该题主要考察的是：成本偏差分析，CV=已完工程计划费用-已完工程实际费用，若CV＜0，证明工程费用超支，已完工程实际费用＞已完工程计划费用；SV=已完工程计划费用-拟完工程计划费用，sv＜0,说明工程进度拖后，拟完工程计划费用＞已完工程计划费用。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]