[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910381":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910381,587,2,"多选题","(2016年)施工成本管理中，企业对项目经理部可控责任成本进行考核的指标有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","直接成本降低率",false,{"key":16,"text":17,"correct":14},"B","预算总成本降低率",{"key":19,"text":20,"correct":21},"C","责任目标总成本降低率",true,{"key":23,"text":24,"correct":21},"D","施工责任目标成本实际降低率",{"key":26,"text":27,"correct":21},"E","施工计划成本实际降低率","CDE","该题主要考察的是：项目经理部可控责任成本考核指标，项目经理部可控责任成本考核指标：(1)项目经理责任目标总成本降低额和降低率；(2)施工责任目标成本实际降低额和降低率；(3)施工计划成本实际降低额和降低率。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]