[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910378":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910378,587,2,"多选题","(2012年)分部分项工程成本分析中，“三算对比”主要是进行()的对比。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","实际成本与投资估算",false,{"key":16,"text":17,"correct":18},"B","实际成本与预算成本",true,{"key":20,"text":21,"correct":14},"C","实际成本与竣工决算",{"key":23,"text":24,"correct":18},"D","实际成本与目标成本",{"key":26,"text":27,"correct":14},"E","施工预算与设计概算","BD","分析的方法是： 进行预算成本、目标成本和实际成本的“三算” 对比，分别计算实际成本与预算成本、实际成本与目标成本的偏差，分析偏差产生的原因， 为今后的分部分项工程成本寻求节约途径。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]