[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910368":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910368,587,2,"多选题","(2014年)根据《建设项目工程总承包合同（示范文本）》，在合同专用条款中应约定预付款的（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","抵扣保证",false,{"key":16,"text":17,"correct":18},"B","抵扣方式",true,{"key":20,"text":21,"correct":18},"C","抵扣比例",{"key":23,"text":24,"correct":18},"D","抵扣时间安排",{"key":26,"text":27,"correct":14},"E","抵扣币种","BCD","该题主要考察的是：预付款抵扣，预付款的抵扣方式、抵扣比例和抵扣时间安排，在专用条款中约定。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]