[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910360":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910360,587,2,"多选题","(2010年)固定资产修理费用于项目生产运营支出的费用，下列关于固定资产修理费的说法中，正确的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","修理费可以预提",true,{"key":16,"text":17,"correct":14},"B","修理费可以摊销",{"key":19,"text":20,"correct":14},"C","修理费可以直接在成本中列支",{"key":22,"text":23,"correct":24},"D","生产运营各年的修理费率必须一致",false,{"key":26,"text":27,"correct":24},"E","修理费应计入总成本费用中的其他费用","ABC","选项D，在生产运营的各年中，修理费率的取值，一般采用固定值。根据项目特点也可以间断性的调整修理费率，开始取较低值，以后取较高值；选项E，修理费允许直接在成本中列支，如果当期发生的修理费用数额较大，可实行预提或摊销的办法。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]