[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910351":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910351,587,2,"多选题","(2015年)下列施工人员意外伤害保险期限的说法，正确的是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","保险期限应在施工合同规定的工程竣工之日二十四时止",true,{"key":16,"text":17,"correct":14},"B","工程量提前竣工的，保险责任自行终止",{"key":19,"text":20,"correct":21},"C","工程因故延长工期的，保险期限自动延长",false,{"key":23,"text":24,"correct":21},"D","保险期限自开工之日起最长不超过三年",{"key":26,"text":27,"correct":21},"E","保险期内工程停工的，保险人应当承担保险责任","AB","本题考查的是与工程项目有关的保险规定。建筑意外伤害保险期限应从施工工程项目被批准正式开工，并且投保人已缴付保险费的次日(或约定起保日) ，零时起，至施工合同规定的工程竣工之日二十四时止。提前竣工的，保险责任自行终止。工程因故延长工期或停工的，需书面通知保险人并办理保险期间顺延手续，但保险期间自开工之日起最长不超过五年。工程停工期间，保险人不承担保险责任。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]