[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910332":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910332,587,2,"多选题","(2011年)价值工程活动过程中，分析阶段的主要工作有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","价值工程对象选择",false,{"key":16,"text":17,"correct":18},"B","功能定义",true,{"key":20,"text":21,"correct":18},"C","功能评价",{"key":23,"text":24,"correct":14},"D","方案评价",{"key":26,"text":27,"correct":14},"E","方案审批","BC","根据表4. 3.1 价值工程的工作程序，分析阶段的工作有：收集整理资料；功能定义；功能整理；功能评价。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]