[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910327":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910327,587,2,"多选题","(2010年)下列方法中，价值工程活动可以用于方案创造的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","专家检查法",true,{"key":16,"text":17,"correct":14},"B","专家意见法",{"key":19,"text":20,"correct":21},"C","流程图法",false,{"key":23,"text":24,"correct":21},"D","列表比较法",{"key":26,"text":27,"correct":21},"E","方案清单法","AB","方案创造的过程是思想高度活跃、进行创造性开发的过程。为了引导和启发创造性的思考，可以采取各种方法，比较常用的方法有以下几种：①头脑风暴法；②歌顿(Gorden)法；③专家意见法；④专家检查法。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]