[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910319":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910319,587,2,"多选题","(2018年)采用总投资收益率指标进行项目经济评价的不足有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","不能用于同行业同类项目经济效果比较",false,{"key":16,"text":17,"correct":14},"B","不能反映项目投资效果的优势",{"key":19,"text":20,"correct":21},"C","没有考虑投资收益的时间因素",true,{"key":23,"text":24,"correct":21},"D","正常生产年份的选择带有较大的不确定性",{"key":26,"text":27,"correct":14},"E","指标的计算过于复杂和繁琐","CD","总投资收益率高于同行业的收益率参考值，表明用总投资收益率表示的项目盈利能力满足要求，A 错；投资收益率指标的经济意义明确、直观，计算简便，E 错。在一定程度上反映了投资效果的优劣，可适用于各种投资规模，B 错。但不足的是，没有考虑投资收益的时间因素，忽视了资金时间价值的重要性；指标计算的主观随意性太强，换句话说，就是正常生产年份的选择比较困难，如何确定带有一定的不确定性和人为因素。因此，以投资收益率指标作为主要的决策依据不太可靠。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]