[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910318":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910318,587,2,"多选题","(2016年)投资方案经济效果评价指标中，既考虑了资金的时间价值，又考虑了项目在整个计算期内经济状况的指标有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","净现值",true,{"key":16,"text":17,"correct":18},"B","投资回收期",false,{"key":20,"text":21,"correct":14},"C","净年值",{"key":23,"text":24,"correct":18},"D","投资收益率",{"key":26,"text":27,"correct":14},"E","内部收益率","ACE","本题考查的是净现值与净年值。动态评价方法考虑资金时间价值，能较全面地反映投资方案整个计算期的经济效果。动态评价指标包括：内部收益率、净现值、净年值等。净现值指标考虑了资金的时间价值，并全面考虑了项目在整个计算期内的经济状况。内部收益率指标考虑了资金的时间价值以及项目在整个计算期内的经济状况。@##",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]