[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910308":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910308,587,2,"多选题","(2010年)下列关于投资项目不确定分析的说法中，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","盈亏平衡分析只适用于项目的财务评价",true,{"key":16,"text":17,"correct":18},"B","敏感性分析只适用于项目的财务评价",false,{"key":20,"text":21,"correct":14},"C","风险分析可同时用于项目的财务评价和国民经济评价",{"key":23,"text":24,"correct":14},"D","盈亏平衡点反映了项目的抗风险能力",{"key":26,"text":27,"correct":14},"E","敏感性分析指标应与确定性经济指标一致","ACDE","盈亏平衡分析只适用于财务评价， 敏感性分析和风险分析可同时用于财务评价和国民经济评价。 P192：盈亏平衡点反映了项目对市场变化的适应能力和抗风险能力。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]