[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910291":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910291,587,2,"多选题","(2018年)某工程网络计划执行到第8 周末检查进度情况见下表（单位：周） 从中可得到的正确结论有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作H 影响总工期1 周",false,{"key":16,"text":17,"correct":18},"B","工作K 提前一周",true,{"key":20,"text":21,"correct":14},"C","工作K 尚有总时差为零",{"key":23,"text":24,"correct":18},"D","工作M 按计划进行",{"key":26,"text":27,"correct":14},"E","工作H 尚有总时差1 周","BD","从表中得知，H 拖后一周，但因为原有一周总时差，故拖后的时间和总时差抵消，现总时差为0，刚好不影响总工期；K 提前一周，总时差由0 变为1；M 刚好按计划进行，总时差不变，仍为2.@##",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]