[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910290":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910290,587,2,"多选题","(2018年)某工作双代号网络计划如下图所示，存在的绘图错误有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","多个起点节点",true,{"key":16,"text":17,"correct":18},"B","多个终点节点",false,{"key":20,"text":21,"correct":18},"C","存在循环回路",{"key":23,"text":24,"correct":14},"D","节点编号有误",{"key":26,"text":27,"correct":14},"E","有多余虚工作","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]