[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910289":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910289,587,2,"多选题","(2015年)某工程时标网络图如下图所示。计划执行到第5周检查实际进度。发现D工作需要3周完成，E工作需1周完成，F工作刚刚开始。由此可以判断出( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","C工作均已完成",true,{"key":16,"text":17,"correct":14},"B","D工程按计划进行",{"key":19,"text":20,"correct":21},"C","E工作提前1周",false,{"key":23,"text":24,"correct":21},"D","F工作进度不影响工期",{"key":26,"text":27,"correct":14},"E","总工期需要延长一周","ABE","本题考查的是网络计划执行中的控制。选项C，E工作按计划完成；选项D，F工作进度影响总工期。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]