[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910288":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910288,587,2,"多选题","(2013年)工程网络计划中，关键工作是指()的工作。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","自由时差最小",false,{"key":16,"text":17,"correct":18},"B","总时差最小",true,{"key":20,"text":21,"correct":14},"C","时间间隔为零",{"key":23,"text":24,"correct":18},"D","最迟完成时间与最早完成时间的差值最小",{"key":26,"text":27,"correct":14},"E","开始接节点和完成点均为关键节点","BD","该题主要考察的是：关键工作的定义,在网络计划中，总时差最小的工作为关键工作。特别的，当网络计划的计划工期等于计算工期时，总时差为零的工作就是关键工作。P128:在双代号网络计划中，关键线路上的节点称为关键节点。关键工作两端的节点必为关键节点，但两端为关键节点的工作不一定是关键工作。关键节点的最迟时间与最早时间的差值最小。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]