[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910286":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910286,587,2,"多选题","（2019年）建设工程组织固定节拍流水施工的特点有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","专业工作队数大于施工过程数",false,{"key":16,"text":17,"correct":18},"B","施工段之间没有空闲时间",true,{"key":20,"text":21,"correct":18},"C","相邻施工过程的流水步距相等",{"key":23,"text":24,"correct":18},"D","各施工段上的流水节拍相等",{"key":26,"text":27,"correct":18},"E","各专业工作队能够在各施工段上连续作业","BCDE","固定节拍流水施工是一种最理想的流水施工方式，其特点如下: 1)所有施工过程在各个施工段上的流水节拍均相等。 2)相邻施工过程的流水步距相等，且等于流水节拍。 3)专业工作队数等于施工过程数，即每一个施工过程成立一个专业工作队，由该队完成相应施工过程所有施工段上的任务。 4) 各个专业工作队在各施工段上能够连续作业，施工段之间没有空闲时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]