[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910284":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910284,587,2,"多选题","(2013年)非节奏流水施工的特点有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各施工段上的流水节拍均相等",false,{"key":16,"text":17,"correct":18},"B","相邻施工过程的流水步距不尽相等",true,{"key":20,"text":21,"correct":18},"C","专业工作队数等于施工过程数",{"key":23,"text":24,"correct":18},"D","施工段之间可能有空闲时间",{"key":26,"text":27,"correct":14},"E","有的专业工作队不能连续作业","BCD","该题主要考察的是：非节奏流水施工的特点 非节奏流水施工的特点：①各施工过程在各施工段的流水节拍不全相等；②相邻施工过程的流水步距不尽相等；③专业工作队数等于施工过程数；③各专业工作队能够在施工段上连续作业，但有的施工段之间可能有空闲时间。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]