[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910278":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910278,587,2,"多选题","(2016年)根据《建筑施工组织设计规范》，单位工程施工组织设计中的施工部署应包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工资源配置计划",false,{"key":16,"text":17,"correct":18},"B","施工进度安排和空间组织",true,{"key":20,"text":21,"correct":18},"C","施工重点和难点分析",{"key":23,"text":24,"correct":18},"D","工程项目管理组织机构",{"key":26,"text":27,"correct":14},"E","施工现场平面布置","BCD","施工部署是对工程项目进行统筹规划和全面安排，包括工程项目施工目标、进度安排和空间组织、施工重点和难点分析、工程项目管理组织机构等。施工部署是施工组织设计的纲领性内容，施工进度计划、施工准备与资源配置计划、施工方法、施工现场平面布置等均应围绕施工部署进行编制和确定。参见教材P93@##",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]