[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910277":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910277,587,2,"多选题","(2015年)下列项目目标控制方法中，可用于控制工程质量的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","S曲线法",false,{"key":16,"text":17,"correct":18},"B","控制图法",true,{"key":20,"text":21,"correct":18},"C","排列图法",{"key":23,"text":24,"correct":18},"D","直方图法",{"key":26,"text":27,"correct":14},"E","横道图法","BCD","本题考查的是建设工程质量管理条例。7.控制图法 前述排列图法、直方图法是质量控制的静态分析方法，反映的是质量在某一段时间里的静止状态。因此，在质量控制中但用静态分析方法是不够的，还必须有动态分析方法。控制图法就是典型的动态分析方法。S曲线法和横道图法可以控制工程进度，不能控制工程质量。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]