[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910275":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910275,587,2,"多选题","(2016年)采用控制图法控制生产过程质量时，说明点子在控制界限内排列有缺陷的情形有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","点子连续在中心线一侧出现7个以上",true,{"key":16,"text":17,"correct":14},"B","连续7个以上的点子上升或下降",{"key":19,"text":20,"correct":21},"C","连续11个点子落在一倍标准偏差控制界限之外",false,{"key":23,"text":24,"correct":21},"D","点子落在两倍标准偏差控制界限之外",{"key":26,"text":27,"correct":21},"E","点子落在三倍标准偏差控制界限附近","AB","点子在控制界限内排列有缺陷，包括以下几种情况：(1)点子连续在中心线一侧出现7个以上；(2)连续7个以上的点子上升或下降；(3)点子在中心线一侧多次出现，如连续11个点中至少有10个点在同一侧，或连续14点中至少有12点、连续17点中至少有14点、连续20点中至少有16点出现在同一侧：(4)点子接近控制界限，如连续3个点中至少有2个点落在二倍标准偏差与三倍标准偏差控制界限之间，或连续7点中至少有3点、连续10点中至少有4点落在二倍标准偏差与三倍标准偏差控制界限之间；(5)点子出现周期性波动。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]