[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910273":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910273,587,2,"多选题","(2010年)应用控制图法控制生产过程质量时，表明点子在控制界限内排列有缺陷的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","点子连续在中心线一侧出现5个以上",false,{"key":16,"text":17,"correct":18},"B","连续7个以上的点子上升或下降",true,{"key":20,"text":21,"correct":14},"C","连续7个点中至少有5个点在同一侧",{"key":23,"text":24,"correct":18},"D","连续3个点落在两倍标准偏差与三倍标准偏差控制界限之间",{"key":26,"text":27,"correct":18},"E","点子出现周期性波动","BDE","点子在控制界限内排列有缺陷，包括以下几种情况：①点子连续在中心线一侧出现7个以上；②连续7个以上的点子上升或下降；③点子在中心线一侧多次出现，如连续11个点中至少有10个点在同一侧；或连续14点中至少有12点、连续17点中至少有14点、连续20点中至少有16点出现在同一侧；④点子接近控制界限，如连续3个点中至少有2个点落在二倍标准偏差与三倍标准偏差控制界限之间；或连续7点中至少有3点、连续10点中至少有4点落在二倍标准偏差与三倍标准偏差控制界限之间；⑤点子出现周期性波动。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]