[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910272":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910272,587,2,"多选题","(2011年)下列建设工程项目目标控制方法中，可用来判断工程进度偏差的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","直方图法",false,{"key":16,"text":17,"correct":18},"B","网络计划法",true,{"key":20,"text":21,"correct":18},"C","S曲线法",{"key":23,"text":24,"correct":18},"D","香蕉曲线法",{"key":26,"text":27,"correct":14},"E","控制图法","BCD","网络计划技术是一种用于工程进度控制的有效方法， 在工程项目目标控制中采用这种方法也有助于工程成本的控制和资源的优化配置。 S曲线可用于控制工程造价和工程进度。与S曲线法相同， 香蕉曲线同样可用来控制工程造价和工程进度。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]