[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910264":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910264,587,2,"多选题","(2010年)建设工程建设与施工采用总分包模式的特点有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对总承包商要求高，业主选择范围小",true,{"key":16,"text":17,"correct":18},"B","总承包合同价格可较早确定，合同金额较低",false,{"key":20,"text":21,"correct":14},"C","业主的合同结构简单，组织协调工作量小",{"key":23,"text":24,"correct":14},"D","工程设计与施工有机融合，有利于缩短建设工期",{"key":26,"text":27,"correct":18},"E","分包单位多，弱化了工程质量控制工作","ACD","采用总分包模式的特点：①有利于项目的组织管理；②有利于控制工程造价；③有利于控制工程质量；④有利于缩短建设工期；⑤对业主而言，选择总承包商的范围小，一般合同金额较高；⑥对总承包商而言，责任重、风险大，需要具有较高的管理水平和丰富的实践经验。当然，获得高额利润的潜力也比较大。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]