[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910260":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910260,587,2,"多选题","关于工程项目后评价的说法，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目后评价应在竣工验收阶段进行",false,{"key":16,"text":17,"correct":18},"B","项目后评价的基本方法是对比法",true,{"key":20,"text":21,"correct":14},"C","项目效益后评价主要是经济效益后评价",{"key":23,"text":24,"correct":18},"D","过程后评价是项目后评价的重要内容",{"key":26,"text":27,"correct":14},"E","项目后评价全部采用实际运营数据","BD","本题考核的知识点为项目后评价。项目后评价是在工程项目竣工验收或通过销售交付使用，经过生产经营或销售取得实际投资效果后，才能进行的评价。项目后评价的基本方法是对比法。项目后评价主要从项目效益后评价和项目过程后评价两个方面进行评价。项目效益后评价具体包括经济效益后评价、环境效益后评价、社会效益后评价、项目可持续性后评价及项目综合效益后评价。项目效益后评价是采用实际运营数据进行评价，而项目过程后评价就不完全采用实际运营数据进行评价。@##",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]