[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910217":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910217,587,2,"多选题","(2009年)按现行规定，建设项目静态投资包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","基本预备费",true,{"key":16,"text":17,"correct":14},"B","因工程量误差引起的造价增长值",{"key":19,"text":20,"correct":14},"C","施工机械租赁费",{"key":22,"text":23,"correct":24},"D","涨价预备费",false,{"key":26,"text":27,"correct":24},"E","建设期贷款利息","ABC","静态投资是指不考虑物价上涨、建设期贷款利息等影响因素的建设投资。静态投资包括：建筑安装工程费、设备和工器具购置费、工程建设其他费、基本预备费， 以及因工程量误差而引起的工程造价增减值等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]