[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910200":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},910200,587,2,"多选题","（2019年）按国际造价管理联合会(ICE C)做出的定义,全面造价管理制止有效利用专业知识与技术，对项目（ ）进行筹划和控制",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","过程",false,{"key":16,"text":17,"correct":18},"B","资源",true,{"key":20,"text":21,"correct":18},"C","成本",{"key":23,"text":24,"correct":18},"D","盈利",{"key":26,"text":27,"correct":18},"E","风险","BCDE","按照国际造价管理联合会(lnternational Cost Engineering Council． ICEC) 给出的定义，全面造价管理 (Total Cost Management, TCM)是指有效地利用专业知识与技术，对资源、成本、盈利和风险进行筹划和控制。建设工程全面造价管理包括全寿命期造价管理、全过程造价管理、全要素造价管理和全方位造价管理。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程造价管理","建筑工程",0]