[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910195":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},910195,587,1,"单选题","（2020年真题）采用挣值分析法，动态监控工程进度和费用时，若在某一时点计算得到费用绩效指数大于1,进度绩效指数小于1,则表明该工程当前的实际状态是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","费用节约，进度提前",false,{"key":16,"text":17,"correct":14},"B","费用超支，进度拖后",{"key":19,"text":20,"correct":21},"C","费用节约，进度拖后",true,{"key":23,"text":24,"correct":14},"D","费用超支，进度超前","P356-360 CIP>1,表示实际费用节约;SPI\u003C1,表示实际进度拖后。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]