[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910183":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},910183,587,1,"单选题","（2018年考题）某工程施工至月底时的情况为：已完工程量120m，实际单价8000元\u002Fm，计划工程量100m，计划单价7500元\u002Fm。则该工程在当月底的费用偏差为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","超支6万元",true,{"key":16,"text":17,"correct":18},"B","节约6万元",false,{"key":20,"text":21,"correct":18},"C","超支15万元",{"key":23,"text":24,"correct":18},"D","节约15万元","费用偏差=已完工程计划费用—已完工程实际费用=120*7500-120*8000=-60000元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]