[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910180":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},910180,587,1,"单选题","（2017年考题）其工程施工至2016年12月底,已完工程计划用2000万元,拟完工程计划费用2500万元,已完工程实际用为1800万元,则此时该工程的费用绩效指数CPI为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.8",false,{"key":16,"text":17,"correct":14},"B","0.9",{"key":19,"text":20,"correct":21},"C","1.11",true,{"key":23,"text":24,"correct":14},"D","1.25","本题考查的是工程费用动态监控。费用绩效指数=已完工程计划费用\u002F已完工程实际费用=2000\u002F1800=1.11。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]