[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910179":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},910179,587,1,"单选题","（2016年考题）某工程施工至某月底，经统计分析得：已完工程计划费用1800万元，已完工程实际费用2200万元，拟完工程计划费用1900万元，则该工程此时的进度偏差是（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","-100",true,{"key":16,"text":17,"correct":18},"B","-200",false,{"key":20,"text":21,"correct":18},"C","-300",{"key":23,"text":24,"correct":18},"D","-400","进度偏差（SV）=已完工程计划费用（BCWP）-拟完工程计划费用（BCWS）=1800-1900=-100（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]