[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910177":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},910177,587,1,"单选题","（2016年考题）按工期-成本同步分析法，造成工程项目实施中出现虚盈现象的原因是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际成本开支小于计划，实际施工进度落后计划",true,{"key":16,"text":17,"correct":18},"B","实际成本开支等于计划，实际施工进度落后计划",false,{"key":20,"text":21,"correct":18},"C","实际成本开支大于计划，实际施工进度等于计划",{"key":23,"text":24,"correct":18},"D","实际成本开支小于计划，实际施工进度等于计划","工期-成本同步分析法是指成本控制与进度控制之间有着必然的同步关系。因为成本是伴随着工程进展而发生的。如果成本与进度不对应，说明工程项目进展中出现虚盈或虚亏的不正常现象。施工成本的实际开支与计划不相符，往往是由两个因素引起的：一是在某道工序上的成本开支超出计划；二是某道工序的施工进度与计划不符。因此，要想找出成本变化的真正原因，实施良好有效的成本控制措施，必须与进度计划的适时更新相结合。选项A所述符合虚盈。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]