[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910168":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},910168,587,1,"单选题","（2018年考题）根据《标准施工招标文件》,合同价格是指（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同协议书中写明的合同总金额。",false,{"key":16,"text":17,"correct":14},"B","合同协议书中写明的不含蓄股价的合同总金额",{"key":19,"text":20,"correct":14},"C","合同协议书中写明的不含蓄列金额的合同总金额",{"key":22,"text":23,"correct":24},"D","承包人完成全部承包工作后的工程估算价格。",true,"合同价格是指承包人按合同约定完成包括缺陷责任期内的全部承包工作后，发包人应付给承包人的金额，包括在履行合同过程中按合同约定进行的变更、价款调整、通过索赔应予补偿的金额。合同价格也是承包人完成全部承包工作后的工程结算价格。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]