[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910163":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},910163,587,1,"单选题","（2015年考题）下列合同计价方式中，建设单位最容易控制造价的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","成本加浮动酬金合同",false,{"key":16,"text":17,"correct":14},"B","单价合同",{"key":19,"text":20,"correct":14},"C","成本加百分比酬金合同",{"key":22,"text":23,"correct":24},"D","总价合同",true,"本题考查的是施工招标策划。在不同的计价方式中，建设单位最容易控制造价的是总价合同，其次是单价合同，最难的是成本加酬金合同。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]