[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910157":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},910157,587,1,"单选题","（2018年考题）下列不同计价方式的合同中。施工承包单位风险大，建设单位容易运行造价控制的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单价合同",false,{"key":16,"text":17,"correct":14},"B","成本加浮动酬金合同",{"key":19,"text":20,"correct":21},"C","总价合同",true,{"key":23,"text":24,"correct":14},"D","成本加百分比酬金合同","",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]