[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910146":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},910146,587,1,"单选题","（2013年考题）根据《建设项目工程总承包合同（示范文本）》，下列关于预付款支付和抵扣的说法，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同约定预付款保函的，发包人应在合同生效后支付预付款",false,{"key":16,"text":17,"correct":18},"B","合同未约定预付款保函的，发包人应在合同生效后10日内支付预付款",true,{"key":20,"text":21,"correct":14},"C","预付款抵扣方式和比例，应在合同通用条款中规定",{"key":23,"text":24,"correct":14},"D","预付款抵扣完后，发包人无需向承包人退还预付款保函","A合同约定预付款保函的，发包人应在合同生效及收到承包人提交的预付款保函后 10日内，根据约定的预付款金额，一次性支付给承包人；B合同未约定预付款保函的，发包人应在合同生效后10日内，根据约定的预付款金额，一次性支付给承包人；C预付款抵扣方式、抵扣比例和抵扣时间安排，应在合同专用条款中约定；D预付款抵扣完后，发包人应及时向承包人退还预付款保函。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]