[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910141":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},910141,587,1,"单选题","（2014年考题）审查工程设计概算时，总概算投资超过批准投资估算（）以上的，需要新上报审批。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5%",false,{"key":16,"text":17,"correct":14},"B","8%",{"key":19,"text":20,"correct":21},"C","10%",true,{"key":23,"text":24,"correct":14},"D","15%","本题考查的是设计概算的审查。对总概算投资超过批准投资估算10%以上的，应进行技术经济论证，重新上报进行审批。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]