[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910091":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},910091,587,1,"单选题","（2016年考题）建筑工程一切险中，安装工程项目的保险金额是该项目的（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","概算造价",false,{"key":16,"text":17,"correct":14},"B","结算造价",{"key":19,"text":20,"correct":21},"C","重置价值",true,{"key":23,"text":24,"correct":14},"D","实际价值","安装工程项目的保险金额为其重置价值。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]